Hope
Township Road Commission Meeting
August 27, 2009
Hope Township Road Committee meeting
Committee members in attendance: Don Dice; Dennis Guthrie; Jim
Hockemeyer; Elgin Childs
Open with the pledge of alliance to the flag
Topic: roads to be considered for 2010
Comment/question
Middle road that dead ends into Shearer - can we put rumble strips
to indicate the end of the road; could you put a guard rail up;
can culverts there be moved
Roads estimates that will be updated or generated
Hull Road (east of Stark)
- $114,000 (2009 estimate)
E. Baker Road (between Stark and Dublin)
- $107,000 (2009 estimate)
Curtis Road (reworked and paved)
- $156,000 (2009 estimate)
If the 2009 road work estimates hold, we should have 18,000-21,000
going into 2010. Should start 2010 with ~$145,000.
Suggestions from the floor:
-
We should consider putting a seal coat on some roads to
help them last longer
Next meeting will be October 29, 7:00 at the Firehouse . This
meeting will be the time the final recommendations for the 2010
spending will come from the Road Committee which will go to the
Township Board.
Meet closed at 7:45
People in attendance:
Andy Kobisa 1160 E. Curtis Road
Steve Wesche 909 Pequot lane
Larry Hall 1802 E. Hull Road
Terry Chrivia 1708 E. Hull Road
Jinelle Chrivia 1708 E. Hull Road
Scott Abbe 1726 E. Baker Road
Gerald Mahl 1696 E. Baker Road
Jocelyn Guthrie 1841 E. Baker Road
Jody Jordan 1858 E. Baker Road
Starla Jordan 1858 E. Baker Road
BACK